NOFO: what is in it?
• More infrastructure-focused.
Why this matters
• Emphasis on construction-ready projects, measurable risk reduction, and implementation readiness . • Only infrastructure and construction projects that have at least conceptual design are eligible. • National Competition projects must include Go/No-Go milestones in the work schedule.
1. Scope, design maturity,
schedule, and documentation must line up earlier.
2. Teams that connect grant
strategy with engineering and delivery planning will be better positioned than teams treating each task separately.
• Simplified scoring for National Competition.
• Hazard mitigation plan development/updates and scoping not directly tied to a specific infrastructure project are not eligible .
• Phased projects are not eligible .