Eligibility Challenges
1. Defined project scope
5. Cost estimate
• Line-item cost estimate • Based on quantities derived from the conceptual design 6. Environmental & permitting pathway • What permits are likely required • Environmental considerations (wetlands, historic, etc.) 7. Schedule • Design → permitting → construction
2. Conceptual plans / drawings
• Concept-level engineering sketches
3. Basis of Design
• Design assumptions • Codes and standards used • Key calculations or modeling approach 4. Engineering analysis • Hydrologic & hydraulic modeling (for flood projects) • Structural concepts (for buildings)
Remember: 30% conceptual design is required for eligibility.